Thursday, April 8, 2010
Catching Up - 4/8/2010
To date :
- Kitchen has been gutted.
- Windows installed and shingled in to the outside.
- Cabinets have been nailed down short of final Venturelli visit to Horgan showroom this weekend.
- Appliances have been ordered. Scheduled for delivery May 5th.
- Counter tops have been determined and are currently out for pricing. Carrera marble everywhere. Two inch material polished on island all others to be 1 1/4" honed.
Extras to date include: Last Updated 4/28/10
- Louvered Vent at Ridge
- Historic trim at new windows
- New windows in 1st floor bath and girls room
- Rot repair at front corner soffit and corner boards
- Floor patch - The wood floor did not extend under the appliances or existing cabinets and will need to be patched in.
- Repair ceiling at dining room where there is previous water damage.
- Kitchen Sink upgrade from allowance.
- Structural work to fix existing floor where flooring is replaced.
Schedule as of today:
- Temp sink installed and existing sink and cabinets torn out. 4/9.
- Stair work & Rough electrical 4/19.
- Rock & Plaster will start 4/26
- Cabinet installation 4/30
- Finish carpentry 5/2
- Counter top installation 5/10
- Painting 5/7