Thursday, April 8, 2010

Catching Up - 4/8/2010

To date :
  • Kitchen has been gutted.
  • Windows installed and shingled in to the outside.
  • Cabinets have been nailed down short of final Venturelli visit to Horgan showroom this weekend.
  • Appliances have been ordered. Scheduled for delivery May 5th.
  • Counter tops have been determined and are currently out for pricing. Carrera marble everywhere. Two inch material polished on island all others to be 1 1/4" honed.
Extras to date include: Last Updated 4/28/10
  • Louvered Vent at Ridge
  • Historic trim at new windows
  • New windows in 1st floor bath and girls room
  • Rot repair at front corner soffit and corner boards
  • Floor patch - The wood floor did not extend under the appliances or existing cabinets and will need to be patched in.
  • Repair ceiling at dining room where there is previous water damage.
  • Kitchen Sink upgrade from allowance.
  • Structural work to fix existing floor where flooring is replaced.
Schedule as of today:
  1. Temp sink installed and existing sink and cabinets torn out. 4/9.
  2. Stair work & Rough electrical 4/19.
  3. Rock & Plaster will start 4/26
  4. Cabinet installation 4/30
  5. Finish carpentry 5/2
  6. Counter top installation 5/10
  7. Painting 5/7