Met last night to go over the shop drawings for the cabinets. Everything was ok'd except colors.
I will go over a few other details with Scott regarding drawer beneath wall ovens and silver dividers as well as pull out shelves in blind base cabinet.
We have a signed change order for replacement windows. (2) in downstairs bath and (2) in girls bedroom.
Schedule: Project should start on 3/22 with cabinets being delivered on 4/14
TODO's:
~ Need to choose paint color for cabinets. Should be Benjamin.
~ Need to pick plumbing fixtures.